According to the "Regulations on the Environmental Protection Management of Construction Projects" and the "Interim Measures for the Environmental Protection Acceptance of Construction Projects", Foryou Industries Co., Ltd. has nominated the "Foryou Industries Co., Ltd. High Precision Die Casting Parts Project (Phase II)" 17# Factory Project Completion Environmental Protection Acceptance Report Form" shall be publicized, and shall be subject to social supervision.

According to the "Regulations on the Environmental Protection Management of Construction Projects" and the "Interim Measures for the Environmental Protection Acceptance of Construction Projects", Foryou Industries Co., Ltd.has nominated the "Foryou Industries Co., Ltd.High Precision Die Casting Parts Project (Phase II)" 17# Factory Project Completion Environmental Protection Acceptance Report Form" shall be publicized, and shall be subject to social supervision.
 
1. Overview of the construction project
 
Foryou Industries Co., Ltd.High Precision Die Casting Parts Project (Phase II) (referred to as the "Phase II Project", the same below) with a total investment of 130 million yuan, a total area of ​​12,180 m2, and a total construction area of ​​31,298 m2. The second phase of the project has 600 new employees, working hours of 300 days and 8 hours of work per day. See Annex 1 for the business license. The main production content of the second phase of the project is to increase the annual production of 6480t aluminum alloy die castings and 2156.45t zinc alloy die castings, which are auto parts. This project was approved by the Zhongkai High-tech Zone Bureau of Huizhou Environmental Protection Bureau in January 2018 (Huizhong Huanjian [2018] No. 28), see Annex 7. Foryou Industries Co., Ltd.carried out the third-phase acceptance of the three plants of the second-phase project 17#, 15#, and 18#. After obtaining the approval, build 17# factory building in advance. As of July 2018, the 17# plant and environmental protection facilities have been completed, and the 15# and 18# plant and environmental protection facilities have not yet been completed. According to relevant laws and regulations, first conduct the completion environmental protection acceptance inspection of the 17# factory building that has been completed and put into trial production, that is, this project (the same below). After the construction is completed, the 15# and 18# factory buildings will be completed according to the corresponding completion environmental protection acceptance procedures. formalities.
 
This project is the first phase acceptance of the second phase of the project. The content of the acceptance is: a 17# factory building, covering an area of ​​3030m2, a building area of ​​3030m2, and a floor height of 16m; an annual output of 6480t aluminum alloy die castings; a total investment of 34.62 million yuan, of which Environmental protection investment is 250,000 yuan.
 
2. Acceptance procedures
 
According to the "Regulations on the Environmental Protection Management of Construction Projects" and the "Interim Measures for the Environmental Protection Acceptance of Construction Projects", after the completion of the project, Foryou Industries Co., Ltd.compiled the "Foryou Industries Co., Ltd.High Precision Die Casting Parts Project (Phase 2) 17# Plant Project Completion Environmental Protection Acceptance Report Form", and an acceptance group including construction units, design units, environmental assessment units, acceptance monitoring units, technical review experts, etc. has been established. After on-site acceptance by the acceptance group, it was agreed that the project passed the acceptance.
 
3. The main issues for soliciting public opinions
 
What are the opinions and requirements of the construction unit regarding environmental protection measures?
 
4. Name and contact information of the project construction unit
 
Construction unit: Huizhou Huayang Precision Machinery Co., Ltd.
 
Contact address: District B, Huayang Industrial Park, No. 1, Shangxia North Road, Dongjiang High-tech Zone, Huizhou City
 
Contact: Ye Yuanyong
 
Phone: 13809838669
 
Five, the main way the public put forward opinions
 
According to the "Interim Measures for the Environmental Protection Acceptance of Construction Projects" and other relevant regulations, the period of this announcement is from October 22, 2018 to November 16, 2018 (20 working days). If any unit or individual has valuable opinions, suggestions or questions about the acceptance of this project, they can give feedback to the construction unit through telephone, letter, etc. during the publicity period, so that the construction unit can adopt and implement the environmental management work in the future.
 